Work package 4

Workpackage number  4

Workpackage title : Project Management

Activity Type MANAG/ OTHER

Participant number

1 SCK•CEN

Total

Person-months per participant:

Man(1.52)/other(0.98)

2.5



Objectives

Overall management of the DETECT project. The management is supported by the DETECT secretariat


Description of work (brief description and month of delivery)

Establishment and operation of the DETECT secretariat

Organisation and delivery of all contractually required documents

Evaluate the success of the working program

Revise the working program if necessary

Prepare a dedicated web portal open/.restricted



Deliverables

D4.1 Preparation of the consortium agreement month 1
D4.2 Web site month 1
D4.3 Project Presentation at month 3
D4.4 Communication Action Plan at month 6
D4.5 Project status report I month 18
D4.6 Project status report I month 30